Eneko One Aldwych London

The Challenge

Eneko at One Aldwych is a Basque-inspired restaurant showcasing the cuisine of renowned chef Eneko Atxa. Situated in the heart of Covent Garden, an area known for its vibrant theatres and constant footfall, the project required a carefully managed fit-out within a busy, high-profile hospitality environment.

Hensall was appointed to deliver a comprehensive range of electrical services as part of the restaurant’s transformation, alongside significant mechanical modifications. A key challenge lay in coordinating the upgrade and integration of new systems within an existing building, requiring the removal and adaptation of legacy infrastructure without disrupting surrounding operations.

The mechanical works were particularly complex, involving the strip-out of existing kitchen and restaurant services, followed by the installation of new supply and extract ventilation systems. This included extensive ductwork routed through constrained spaces to serve both the main kitchen and dining areas. In addition, existing drainage systems required removal, rerouting, and extension to accommodate new layouts, while hot and cold water services had to be precisely coordinated to serve specialist kitchen equipment and a new mezzanine bar area.

Further challenges included the installation of a new gas control system for the kitchen and modifications to the existing building management system (BMS), ensuring that all new and adapted services were fully integrated and operational within the wider building controls.

From an electrical standpoint, the project demanded a high level of detail and coordination. The installation included full electrical distribution and containment systems, small power, and bespoke feature lighting designed to enhance the restaurant’s atmosphere. Lighting control systems needed to deliver flexibility for different dining experiences, while essential systems such as emergency lighting, fire alarms, security alarms, CCTV, IT/data infrastructure, and AV systems had to be seamlessly incorporated.

Delivering these works within a prestigious central London location, alongside tight programme constraints and the expectations of a high-end dining venue, required careful planning, precision engineering, and close collaboration across all project stakeholders.

Our Solution

Hensall successfully delivered a coordinated mechanical and electrical installation for Eneko at One Aldwych, transforming the space into a high-end dining destination that reflects the vision of Eneko Atxa.

The project encompassed a wide range of services, including a full lighting installation designed to complement the restaurant’s ambience, alongside essential safety and security systems such as fire alarms, security alarms, and CCTV. Hensall also installed supply and extract ventilation systems critical to the efficient operation of the kitchen, as well as domestic hot and cold water services to support both kitchen and bar areas.

One of the most significant logistical challenges was the restaurant’s location, situated two storeys below street level in the heart of Covent Garden. With limited access, all materials and equipment had to be carefully lowered from street level, requiring detailed planning and coordination to maintain programme timelines and ensure safe handling throughout the installation process.

In response to the architectural design, which featured acoustic ceilings throughout much of the venue, Hensall developed bespoke lighting housings to accommodate each luminaire specification. This ensured that the lighting design intent was achieved without compromising the acoustic performance of the space—an essential consideration in creating the desired dining atmosphere.

Despite the constraints and complexity of the site, Hensall delivered the project efficiently and within the agreed timeframe. The completed installation met the highest standards of quality and functionality, contributing to the successful transformation of the venue into a thriving and luxurious restaurant, much to the satisfaction of the client.

Length of Job 7 Months
M&E Value £300,000
Completed Date May 2016
Client Eneko One Aldwych London
Electrical Project Manager

Tony Smith

Mechanical Project Manager

“One Aldwych is one of the most prestigious hotels in London and so our guests tend to appreciate high attention to detail. HENSALL were outstanding throughout the project and delivered a stunning fit out that has left many of our guests totally speechless.”

ONE ALDWYCH

Have a project in mind?

Our team delivers efficient, high-quality refurbishments tailored to your project needs. Get in touch to discuss how we can support your vision.

Contact us at info@hensall.com
or call us on 01977 661318